EVN expects a difficult 2027 power supply because of El Nino. Here is a month-by-month plan for businesses to prepare backup power before April 2027.

Industry News3 min readPowerGenerator Editorial Team
Illustration: Vietnam's 2027 Dry Season: When to Start Your Backup Power Plan

April 2027 deserves a circle on every plant engineer's calendar. It is the deadline EVN has set for finishing its major repair program, and it also opens the hot months when electricity-saving targets are at their toughest. For a business that cannot afford to stop, the four months between now and then are the right window to test backup power, rather than discovering a weak battery during an outage.

Why 2027 is getting attention

Speaking at the National Energy Security Forum in Hanoi on 10 November, EVN Deputy General Director Nguyen Tai Anh said next year's supply is forecast to be difficult, mainly because of El Nino. Demand is climbing at the same time: commercial electricity in the first ten months of 2026 was 9.84% higher than a year earlier.

One point matters when reading this news. EVN has not published any power-cut schedule for the 2027 dry season. Treat the forecast as a reason to get ready, not as a reason to rush out and buy another generator.

What is happening on the supply side

Area EVN's stated plan
Hydropower Fill reservoirs close to normal water level and hold them high through late 2026
Unit repairs Start in November 2026, complete major work before April 2027
Coal EVN plants have signed 2027 supply contracts
LNG Contracts expected to close in November 2026
New capacity Aiming to run both Quang Trach I units this year, with the Tri An expansion generating in 2027
Battery storage 140 MW of BESS running in the North and Hanoi as of end-September 2026

Which customers should pay closest attention

Directive 10/CT-TTg of 30 March 2026 calls for saving at least 3% of electricity over the full year and 10% during the hot months from April to July. Sites consuming 500,000 kWh or more per year are a particular focus. If your factory is in that group, work out in advance how you would operate if asked to adjust load.

A suggested preparation calendar

What follows is our editorial view, not advice from EVN.

December: assess. List the loads that must never lose power, then compare them with the industrial generators you already have. If production lines were added after the set was installed, redo the sizing using this guide on how to calculate generator capacity.

January: close the gaps. A set expected to run long hours through peak periods needs the right rating, because standby units are not built for regular duty. This guide explains how Prime and Standby power differ, which helps when comparing quotations.

February: service. Inspect batteries, lubricating oil, coolant, filters and the quality of fuel sitting in the tank. Without an in-house team, book generator maintenance services early, before technicians are stretched by peak-season demand.

March: rehearse. Run the set under load and simulate a mains failure to confirm that the ATS panel transfers correctly. Short-term projects that do not justify a purchase can look at generator rental instead.